Calculate sprints for a release

Let's say 1 story point of work takes 1 ideal day. 1 ideal day = 8 hrs. An ideal day is a day without any hinderance and fully dedicated to project development work. Let's assume 1 ideal day = 2 actual days.

Suppose for release 1, there are 200 story points of work. If one person does the work, the work will get completed in 400 days. We have 5 people in the sprint. So the release will take 80 days. If we take a 2 week sprint i.e. 10 days, 8 sprints will be required.